Fukushima Daiichi Nuclear Power Station Current status of restoration work
![Reactor buildings of Unit 1 and 2 Reactor buildings of Unit 1 and 2](/library/110517/110517_1.jpg)
Reactor buildings of Unit 1 and 2
pictured on May 06,2011
![Truck with nitrogen supply equipment Truck with nitrogen supply equipment](/library/110517/110517_2.jpg)
Truck with nitrogen supply equipment
pictured on May 06,2011
![Car swept up by Tsunami Car swept up by Tsunami](/library/110517/110517_3.jpg)
pictured on May 06,2011
![Removal of rubble by an unmanned heavy machinery Removal of rubble by an unmanned heavy machinery](/library/110517/110517_4.jpg)
Removal of rubble by an unmanned heavy machinery
pictured on May 06,2011
![Crawler dump truck for spraying dust inhibitor Crawler dump truck for spraying dust inhibitor](/library/110517/110517_5.jpg)
Crawler dump truck for spraying dust inhibitor
pictured on May 06,2011
![Spraying dust inhibitor by a crawler dump truck Spraying dust inhibitor by a crawler dump truck](/library/110517/110517_6.jpg)
Spraying dust inhibitor by a crawler dump truck
pictured on May 06,2011
![Water spray to the spent fuel pool of Unit 4 by a concrete pumping vehicle Water spray to the spent fuel pool of Unit 4 by a concrete pumping vehicle](/library/110517/110517_7.jpg)
Water spray to the spent fuel pool of Unit 4 by a concrete pumping vehicle
pictured on May 06,2011
![Temporary substation for Unit 1 and 2 Temporary substation for Unit 1 and 2](/library/110517/110517_8.jpg)
Temporary substation for Unit 1 and 2
pictured on May 06,2011
![Concrete placement to the vertical shaft of Unit 2 (1) Concrete placement to the vertical shaft of Unit 2 (1)](/library/110517/110517_9.jpg)
Concrete placement to the vertical shaft of Unit 2 (1)
pictured on May 06,2011
![Concrete placement to the vertical shaft of Unit 2 (2) Concrete placement to the vertical shaft of Unit 2 (2)](/library/110517/110517_10.jpg)
Concrete placement to the vertical shaft of Unit 2 (2)
pictured on May 06,2011
![Dust inhibitor sprayed around the circulating water pump of Unit 3 Dust inhibitor sprayed around the circulating water pump of Unit 3](/library/110517/110517_11.jpg)
Dust inhibitor sprayed around the circulating water pump of Unit 3
pictured on May 06,2011
![Cable trench pit for the water intake of Unit 2 Cable trench pit for the water intake of Unit 2](/library/110517/110517_12.jpg)
Cable trench pit for the water intake of Unit 2
pictured on May 06,2011
![Screen room of Unit 2 Screen room of Unit 2](/library/110517/110517_13.jpg)
pictured on May 06,2011
![Steel sheet piles at the water intake of Unit 2 Steel sheet piles at the water intake of Unit 2](/library/110517/110517_14.jpg)
Steel sheet piles at the water intake of Unit 2
pictured on May 06,2011
![Silt fence installed around the water intake of Unit 2 Silt fence installed around the water intake of Unit 2](/library/110517/110517_15.jpg)
Silt fence installed around the water intake of Unit 2
pictured on May 06,2011
![Temporary motor driven pump for water injection to the reactors of Unit1 to 3 Temporary motor driven pump for water injection to the reactors of Unit1 to 3](/library/110517/110517_16.jpg)
Temporary motor driven pump for water injection to the reactors of Unit1 to 3
pictured on May 06,2011
![Heavy oil tank swept up by Tsunami Heavy oil tank swept up by Tsunami](/library/110517/110517_17.jpg)
Heavy oil tank swept up by Tsunami
pictured on May 06,2011
![Suppression pool's water surge-tank near Unit 5 and 6 Suppression pool's water surge-tank near Unit 5 and 6](/library/110517/110517_18.jpg)
Suppression pool's water surge-tank near Unit 5 and 6
pictured on May 06,2011
![Ultrahigh voltage switching station of Unit 5 and 6 Ultrahigh voltage switching station of Unit 5 and 6](/library/110517/110517_19.jpg)
Ultrahigh voltage switching station of Unit 5 and 6
pictured on May 06,2011
![Temporary tank installed near Unit 5 and 6 (1) Temporary tank installed near Unit 5 and 6 (1)](/library/110517/110517_20.jpg)
Temporary tank installed near Unit 5 and 6 (1)
pictured on May 06,2011
![Temporary tank installed near Unit 5 and 6 (2) Temporary tank installed near Unit 5 and 6 (2)](/library/110517/110517_21.jpg)
Temporary tank installed near Unit 5 and 6 (2)
pictured on May 06,2011
![Building for diesel generator 6B of Unit 6 Building for diesel generator 6B of Unit 6](/library/110517/110517_22.jpg)
Building for diesel generator 6B of Unit 6
pictured on May 06,2011
![Rubble container Rubble container](/library/110517/110517_23.jpg)
pictured on May 06,2011
![Transfer of container Transfer of container](/library/110517/110517_24.jpg)
pictured on May 06,2011
![Administration Office Building (exterior) Administration Office Building (exterior)](/library/110517/110517_25.jpg)
Administration Office Building (exterior)
pictured on May 06,2011
![Administration Office Building (interior 1) Administration Office Building (interior 1)](/library/110517/110517_26.jpg)
Administration Office Building (interior 1)
pictured on May 06,2011
![Administration Office Building (interior 2) Administration Office Building (interior 2)](/library/110517/110517_27.jpg)
Administration Office Building (interior 2)
pictured on May 06,2011
![1st floor of the turbine building of Unit 1(1) 1st floor of the turbine building of Unit 1(1)](/library/110517/110517_28.jpg)
1st floor of the turbine building of Unit 1(1)
pictured on May 06,2011
![1st floor of the turbine building of Unit 1(2) 1st floor of the turbine building of Unit 1(2)](/library/110517/110517_29.jpg)
1st floor of the turbine building of Unit 1(2)
pictured on May 06,2011
![Local exhauster installed in the turbine building of Unit 1 Local exhauster installed in the turbine building of Unit 1](/library/110517/110517_30.jpg)
Local exhauster installed in the turbine building of Unit 1
pictured on May 06,2011
![Positive pressure room installed at the turbine building of Unit 1 Positive pressure room installed at the turbine building of Unit 1](/library/110517/110517_31.jpg)
Positive pressure room installed at the turbine building of Unit 1
pictured on May 06,2011
![Entrance of Main Anti-Earthquake Building(A prefabricated house used for access control) Entrance of Main Anti-Earthquake Building(A prefabricated house used for access control)](/library/110517/110517_32.jpg)
Entrance of Main Anti-Earthquake Building(A prefabricated house used for access control)
pictured on May 06,2011
![Measurement of radioactivity in Main Anti-Earthquake Building Measurement of radioactivity in Main Anti-Earthquake Building](/library/110517/110517_33.jpg)
Measurement of radioactivity in Main Anti-Earthquake Building
pictured on May 06,2011
![Spare protective equipments(1) Spare protective equipments(1)](/library/110517/110517_34.jpg)
Spare protective equipments(1)
pictured on May 06,2011
![Spare protective equipments(2) Spare protective equipments(2)](/library/110517/110517_35.jpg)
Spare protective equipments(2)
pictured on May 06,2011
![Entrance of Main Anti-Earthquake Building(from inside) Entrance of Main Anti-Earthquake Building(from inside)](/library/110517/110517_36.jpg)
Entrance of Main Anti-Earthquake Building(from inside)
pictured on May 06,2011
![Emergency headquarters Emergency headquarters](/library/110517/110517_37.jpg)
pictured on May 06,2011
![Water supply area of Main Anti-Earthquake Building Water supply area of Main Anti-Earthquake Building](/library/110517/110517_38.jpg)
Water supply area of Main Anti-Earthquake Building
pictured on May 06,2011
![Passing forward daily commodities in Main Anti-Earthquake Building Passing forward daily commodities in Main Anti-Earthquake Building](/library/110517/110517_39.jpg)
Passing forward daily commodities in Main Anti-Earthquake Building
pictured on May 06,2011
![Encouraging messages posted on the walls of Main Anti-Earthquake Building Encouraging messages posted on the walls of Main Anti-Earthquake Building](/library/110517/110517_40.jpg)
Encouraging messages posted on the walls of Main Anti-Earthquake Building
pictured on May 06,2011
Fukushima Daiichi Nuclear Power Station Current status of restoration work
Video on May 06,2011