2024.9.26
|
Completion of spent fuel transportation to the Recyclable-Fuel Storage Center of Recyclable-Fuel Storage Company (RFS)
|
2024.9.17
|
Transporting spent fuel in the Unit 7 to the Unit 3
|
2020.9.15
|
Secondary Treatment Performance Confirmation Tests on ALPS-treated water at the Fukushima Daiichi Nuclear Power Station
|
2020.8.3
|
Unit 3 fuel removal work at the Fukushima Daiichi Nuclear Power Station
|
2020.6.11
|
Completion of the Internal Investigation of the Unit 2 Spent Fuel Pool (SFP) at the Fukushima Daiichi Nuclear Power Station
|
2020.6.11
|
Completion of air mortar injection into the Fukushima Daiichi Nuclear Power Station Unit 1 SFP cover bag
|
2020.6.10
|
Start of Internal Investigation of the Fukushima Daiichi Nuclear Power Station Unit 2 Spent Fuel Pool (SFP)
|
2020.5.13
|
Submersible ROV Operation Training in Preparation for the Unit 2 Spent Fuel Pool Internal Investigation at the Fukushima Daiichi Nuclear Power Station
|
2020.5.1
|
Completion of the Unit 1/2 exhaust stack dismantling at the Fukushima Daiichi Nuclear Power Station
|
2020.4.29
|
Dismantling of the Unit 1/2 exhaust stack 23rd block at the Fukushima Daiichi Nuclear Power Station
|
2019.12.4
|
Dismantling of the Unit 1/2 exhaust stack at the Fukushima Daiichi Nuclear Power Station (work on December 4)
|
2019.12.4
|
Dismantling of the Unit 1/2 exhaust stack at the Fukushima Daiichi Nuclear Power Station (work on December 3)
|
2018.5.28
|
Wall Dismantling Work to create an Opening in the West Wall of Unit 2 Reactor Building
|
2018.2.21
|
Installation of all Dome Roof Segments for Unit 3 Spent Fuel Removal Completed
|
2017.11.20
|
Installation of the crane for fuel removal at Fukushima Daiichi NPS Unit 3
|
2017.11.12
|
Installation of the fuel handling machine for fuel removal at Fukushima Daiichi NPS Unit 3
|
2017.11.9
|
Fuel handling machine and crane installation for Unit 3 spent fuel removal
|
2017.9.7
|
Installation of Unit 3 spent fuel removal cover dome roof at Fukushima Daiichi Nuclear Power Station (Second unit)
|
2017.8.22
|
Phase 3 freezing of Landside Impermeable Wall starts at Fukushima Daiichi Nuclear Power Station
|
2017.8.2
|
Installation of Unit 3 spent fuel removal cover dome roof at Fukushima Daiichi Nuclear Power Station (On-site demonstration)
|
2017.7.31
|
Installation of Unit 3 fuel removal cover dome roof at Fukushima Daiichi Nuclear Power Station (First unit)
|
2017.6.27
|
Installation of the cover for Unit 3 spent fuel removal at Fukushima Daiichi Nuclear Power Station
|
2017.3.2
|
Construction of a steel frame to support fuel handling machine began during the new roof installation for Unit 3 spent fuel removal
|
2017.1.17
|
Construction of a new roof for Unit 3 spent fuel removal began at Fukushima Daiichi Nuclear Power Station
|
2016.12.26
|
Completion of drilling a hole toward investigation inside Unit 2 Primary Containment Vessel (PCV) at Fukushima Daiichi Nuclear Power Station
|
2016.12.24
|
Completion of drilling a hole toward investigation inside Unit 2 Primary Containment Vessel (PCV) at Fukushima Daiichi Nuclear Power Station
|
2016.11.10
|
Removal of all wall panels (18 in total) from the Unit 1 reactor building cover completed at Fukushima Daiichi Nuclear Power Station
|
2016.10.20
|
Examination of the Interior of Units 1 and 2 Exhaust Stack Using Drones at Fukushima Daiichi Nuclear Power Station
|
2016.10.7
|
Removal of the 8th wall panel over Unit 1 reactor building at Fukushima Daiichi Nuclear Power Station
|
2016.9.21
|
Conditions of the bank protection area at Fukushima Daiichi Nuclear Power Station (2)
|
2016.9.21
|
Conditions of the bank protection area at Fukushima Daiichi Nuclear Power Station
|
2016.9.13
|
First Wall Panel Removal from Unit 1 Building Cover at Fukushima Daiichi Nuclear Power Station
|
2016.9.9
|
Water level measurement in the drain sump pit of Units 1-2 exhaust stack at Fukushima Daiichi Nuclear Power Station
|
2016.9.5
|
Progress of on-site preparation work (opening of the pit cover) to examine the drain sump pit of Units 1-2 exhaust stack at Fukushima Daiichi Nuclear Power Station
|
2016.8.26
|
Start of on-site preparation work (opening of the pit cover) to examine the drain sump pit of Units 1-2 exhaust stack at Fukushima Daiichi Nuclear Power Station
|
2016.6.6
|
Phase 2 freezing of Landside Impermeable Wall starts at Fukushima Daiichi Nuclear Power Station
|
2016.4.12
|
Shielding Installation on the Top Floor of Unit 3 Reactor Building
|
2016.4.7
|
A Week After the Official Activation of Landside Impermeable Wall (frozen soil wall, or "ice wall")
|
2016.4.6
|
Start of Nozzle Unit Installations for Mist Sprinkler Associated with the Dismantling of Unit 1 Reactor Building Cover
|
2016.3.31
|
Freezing Started for the Landside Impermeable Wall at Fukushima Daiichi Nuclear Power Station
|
2016.2.23
|
Decontamination Work Conducted by the Dry Ice Blast Decontamination Equipent for High Places
|
2015.10.29
|
Completion of Dismantling Flange Tanks in the H1 East Tank Area at Fukushima Daiichi Nuclear Power Station
|
2015.10.26
|
Completion of Seaside Impermeable Wall Closure at Fukushima Daiichi Nuclear Power Station
|
2015.10.6
|
Completion of Roof Panel Removal from Unit 1 Building Cover at Fukushima Daiichi Nuclear Power Station
|
2015.9.15
|
Completion of Pouring the Brine on the Landside of the Landside Impermeable Wall (Ice Wall)
|
2015.9.14
|
Operational Start of Discharging Groundwater from a Temporary Water Storage Tank through the Subdrain Water Treatment Facilities
|
2015.9.10
|
Closing Operation of the Seaside Impermeable Wall at Fukushima Daiichi Nuclear Power Station
|
2015.8.27
|
Filling Up Inside Unit 3 Seawater Piping Trench At Fukushima Daiichi Nuclear Power Station
|
2015.8.4
|
(2015.8.6 video added) Investigation Results Inside of the Unit 3 Spent Fuel Pool
|
2015.8.2
|
Completion of removal of Fuel Handling Machine from Fukushima Daiichi Unit 3 Spent Fuel Pool
|
2015.5.27
|
Operational Start of Dismantling the H2 area tank at Fukushima Daiichi Nuclear Power Station
|
2015.5.15
|
Start Dismantling Unit 1 Reactor Building Cover <Start Sprinkling Anti-scattering Agent>
|
2015.4.28
|
Coolant Functioning Test of Land-side Impermeable Wall (Frozen Soil Wall)
|
2015.2.27
|
Completion of Unit 3 Reactor Opening at Fukushima Daini Nuclear Power Station
|
2015.2.9
|
Unit 3 Trench-Filling operation
|
2015.2.9
|
Development for fuel debris detection technology for reactor at Fukushima Daiichi Nuclear Power Station (Unit 1)
|
2014.12.4
|
Restoring roof panels for the demolition of Unit 1 reactor building cover at Fukushima Daiichi NPS
|
2014.11.10
|
Removing the roof panels of Unit 1 reactor building cover (the 2nd panel)
|
2014.10.31
|
Removing the roof panels of Unit 1 reactor building cover (the south 3 roof panel)
|
2014.10.28
|
Enlarged Opening on the Roof Panels at the Demolition Work of Unit 1 Reactor Building Cover
|
2014.10.22
|
Dismantling of Unit 1 reactor building cover
|
2014.9.30
|
About the completion of the countermeasure work to address the downward flow of strontium present in the soil in relation to the leak in H4 area tank
|
2014.7.17
|
Replacing Drainage Channel Outlet to the Port For Drainage B and C
|
2014.6.12
|
Started building of frozen wall (Ice wall)
|
2014.5.21
|
Groundwater bypass at Fukushima Daiichi Nuclear Power Station (water discharge)
|
2014.4.17
|
Pictures of Installation/ Draining of Ready-Made Contaminated Water Storage Tanks at Fukushima Daiichi NPS
|
2014.4.9
|
Start of pump-up work for beginning the operation of groundwater bypass at Fukushima Daiichi Nuclear Power Station
|
2013.12.27
|
Tank installation, measures against rainwater, and work to have drainage channels covered, at Fukushima Daiichi NPS (Video)
|
2013.11.29
|
Fuel removal work at Fukushima Daiichi NPS Unit 4 (Cask transfer at common pool)
|
2013.11.27
|
Decontamination work on the first floor at Unit 2 reactor building in Fukushima Daiichi NPS
|
2013.11.27
|
Fuel removal work (extraction of spent fuel) at Fukushima Daiichi NPS Unit 4 (video taken underwater)
|
2013.11.26
|
Fuel removal work (extraction of spent fuel) at Fukushima Daiichi NPS Unit 4
|
2013.11.22
|
Fuel removal work at the common pool in Fukushima Daiichi NPS Unit 4
|
2013.11.21
|
Fuel removal work (cask transfer) at Fukushima Daiichi NPS Unit 4
|
2013.11.20
|
Extraction of fuel from Unit 4 (video taken underwater)
|
2013.11.18
|
Current Status of Fukushima Daiichi NPS Unit 4 Fuel Removal
|
2013.11.15
|
Operation of Fuel Removal from Unit 4 Spent Fuel Pool at Fukushima Daiichi NPS
|
2013.11.13
|
Operation to Remove Spent Fuel from Unit 4 Spent Fuel Pool at Fukushima Daiichi NPS
|
2013.10.25
|
Precautionary Measures of Accumulated Water inside the Dike against Typhoon No.27 (Francisco) at Fukushima Daiichi NPS
|
2013.10.17
|
Completion of fuel transfer at Unit 2 in Fukushima Daini Nuclear Power Station
|
2013.10.16
|
Pumping up of rainwater inside the dike in reaction to the approaching Typhoon No. 26 (Wipha)
|
2013.9.25
|
Progress Report on a Cover Installation for Fuel Removal at Unit 4 at Fukushima Daiichi NPS-Completion of Overhead Crane Installation-
|
2013.9.19
|
Work Progress in Dismantlement of the Tank No.5 in H4 Tank Area
|
2013.9.18
|
Dismantlement of the Tanks No. 10 and No.5 in H4 Tank Area
|
2013.9.13
|
Dismantlement of the tank No.10 in H4 tank area
|
2013.9.10
|
Unit 3 Reactor Building, at Fukushima Daiichi Nuclear Power Station, The Bent-Down Tip Jib Mast and Main Mast of a Remote Control Large-Scale Crane
|
2013.9.2
|
Results of Tank Patrol at Fukushima Daiichi Nuclear Power Station
|
2013.8.26
|
Removal of Obstacles Including Debris, etc., at the Southwest Side on the First Floor of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2013.8.15
|
Installation of Permanent Monitoring Instrument of Unit 2 PCV at Fukushima Daiichi Nuclear Power Station
|
2013.8.15
|
Commencement of Pumping up of Groundwater from the Well Point (Partial) between the Water Intake Channel of Unit 1 and 2 at Fukushima Daiichi Nuclear Power Station
|
2013.8.9
|
Condition of Radioactive Density of the Groundwater and the Seawater at the East Side of Turbine Buildings
|
2013.7.22
|
Completion of Outer Wall and Exterior Roof Panel Installation for the Fuel Removal Cover at Unit 4 in Fukushima Daiichi Nuclear Power Station
|
2013.7.17
|
Ground Improvement Construction (Chemical Injection) at Bank Protection between the Water Intake Channel of Unit 1 and Unit 2 at Fukushima Daiichi Nuclear Power Station(Video taken on July 6, 2013)
|
2013.7.12
|
Current status of Fukushima Daini Nuclear Power Station (July 2013)
|
2013.7.9
|
Ground Improvement Construction (Chemical Injection) at Bank Protection between the Water Intake Channel of Unit 1 and Unit 2 at Fukushima Daiichi Nuclear Power Station
|
2013.6.28
|
Foundation Concrete Placing Work Started at the Miscellaneous Solid Waste Incineration Building
|
2013.4.26
|
Removal of the Guide Pipe (Used for PCV Inside Investigation) from Unit 2 PCV at Fukushima Daiichi Nuclear Power Station
|
2013.4.22
|
Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2013.4.11
|
Progress of the Steel Frame Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station
|
2013.4.4
|
Transportation of a Dry Storage Cask from the Common Pool Building to the Temporary Dry Cask Storage Facility in Fukushima Daiichi Nuclear Power Station
|
2013.3.26
|
Hole Drilling for the Investigation of Unit 2 Torus Room at Fukushima Daiichi Nuclear Power Station
|
2013.3.13
|
Steel Frame Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station:Completion of the Third Layer of Steel Frame
|
2013.3.4
|
Completion of Water Stop Work at the Location Where Water Inflow into Unit 3 Radioactive Waste Underground Storage Facility Building was Found at Fukushima Daiichi Nuclear Power Station
|
2013.2.6
|
Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: January 2013)
|
2013.2.6
|
Debris Removal from the Upper part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station: Removal of Steel Truss Debris
|
2013.2.1
|
Photos of the Accident at Fukushima Daiichi Nuclear Power Station (Publicized on February 1, 2013)
|
2013.1.15
|
Steel Framing Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station: Completion of the First Layer of Steel Framing
|
2013.1.9
|
Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: December 2012)
|
2013.1.8
|
Steel Framing Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station: Installation of 2 Columns of the First Layer
|
2012.12.20
|
Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station: Removal of the Steel Beam Which Fell into the Pool
|
2012.12.19
|
Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station: Removal of the Steel Beam Which Fell into the Pool
|
2012.12.5
|
Completion of Water Stop Work at Unit 3 Control Building at Fukushima Daiichi Nuclear Power Station
|
2012.12.5
|
Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: November 2012)
|
2012.11.2
|
Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: October 2012)
|
2012.10.15
|
Duct Replacement at Unit 2 PCV Gas Control System at Fukushima Daiichi Nuclear Power Station
|
2012.10.3
|
Unit 2 RPV Alternative Thermometer Installation at Fukushima Daiichi Nuclear Power Station
|
2012.10.2
|
Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: September 2012)
|
2012.9.14
|
Removal work of the head of RPV at Unit 4 Fukushima Daini Nuclear Power Station
|
2012.9.13
|
Removal of the RPV Lid in the Upper Part of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2012.9.10
|
Damage of Unit 2 PCV Gas Control System Duct at Fukushima Daiichi Nuclear Power Station
|
2012.9.10
|
Current Condition of Fukushima Daiichi Nuclear Power Station
|
2012.9.10
|
Opening Unit 4 Reactor at Fukushima Daini Nuclear Power Station
|
2012.8.10
|
Removal of PCV Lid from the Upper Part of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2012.8.9
|
Reliability Improvement of the Second Cesium Absorption Apparatus
|
2012.7.19
|
Unused Fuel Removal from Unit 4 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station
|
2012.7.18
|
Progress Status of Covering the Marine Soil of the Port of Fukushima Daiichi Nuclear Power Station
|
2012.7.11
|
Completion of Debris Removal from the Upper Part of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2012.6.26
|
Current Condition of Fukushima Daiichi Nuclear Power Station
|
2012.6.15
|
The Protection Platform Installation on Unit 4 Spent Fuel Pool at Fukushima Daiichi Power Station
|
2012.6.12
|
Reliability Enhancement Work for the Cesium Absorption Apparatus
|
2012.5.16
|
Progress Status of Covering the Marine Soil of the Port of Fukushima Daiichi Nuclear Power Station
|
2012.4.26
|
Regarding the treatment of certain areas of the Seismic isolated building of the Fukushima Daiichi Nuclear Power Station as “Uncontrolled area”
|
2012.4.16
|
General Plan and Start of Main Work of the Cover for Fuel Removal of Unit 4 in Fukushima Daiichi Nuclear Power Station
|
2012.4.16
|
Set up of Manned Heavy Machinery on the upper side of Unit 4 Reactor Building In the Fukushima Daiichi Nuclear Power Station
|
2012.3.27
|
Dose measurement work inside of the primary containment vessels of unit 2 of Fukushima Daiichi NPS
|
2012.3.13
|
Ocean soil covering work in front of the intake channel of Fukushima Daiichi Nuclear Power Station Situation of the field test construction and covering condition
|
2012.3.6
|
Removal Works of Debris on the Upper Part of the Reactor Building of Unit 4 in Fukushima Daiichi Nuclear Power Station
|
2012.2.21
|
Fukushima Daiichi Nuclear Power Plant Start of marine soil coating construction inside the port
|
2012.2.3
|
Radiation dose reduction by collecting dust and small rubbles at the parking lot in front of Main Anti-Earthquake Building of Fukushima Daiichi Nuclear Power Station
|
2012.2.1
|
Measures against Freeze of Water Treatment Facility / Measures against Freeze of Reactor Water Injection System at Fukushima Daiichi Nuclear Power Station
|
2012.1.20
|
Current Status of Fukushima Daiichi Nuclear Power Station by photographs
|
2012.1.16
|
Scenery of obstacle removal by crane barge at intake cannel of Unit 1 to 4
|
2011.12.17
|
Current view of Fukushima Daiichi Nuclear Power Plant
|
2011.11.30
|
Establishment of New Routes for Nitrogen Injection into RPV at Units 1-3 of Fukushima Daiichi Nuclear Power Station
|
2011.11.29
|
Resumption of desalting by ion exchanging device at spent fuel pool of Unit4 at Fukushima Daiichi Nuclear Power Plant
|
2011.11.22
|
Unit 3, Fukushima Daiichi Nuclear Power Station Wiping work of rails for the equipment hatch, the Pressure Containment Vessel
|
2011.11.19
|
Debris removal works with heavy machinery at Fukushima Daiichi Nuclear Power
|
2011.11.16
|
Survey and Cleaning in Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2011.11.7
|
Installation Status of Radioactive Material Removal Facility at the Unit 2's Spent Fuel Pool of Fukushima Daiichi Nuclear Power Station
|
2011.11.5
|
Obstacle Removal by Robot and Radiation Dose Measurement after the Removal on the First Floor of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station
|
2011.11.2
|
Overview of the blocking operation of the units 1 - 4 openings
|
2011.10.28
|
Ancillary facilities for cover panels of Unit 1(Completion of Cover Construction at Reactor Building of Unit 1 of Fukushima Daiichi NPS)
|
2011.10.15
|
Current Situation of Fukushima Daiichi Nuclear Power Plant in Pictures -J Village Edition
|
2011.10.14
|
Completion of installing the roof panel of the cover for the reactor building at Unit 1
|
2011.10.11
|
Overview of dust sampling at the openings of Unit 1 Reactor Building in Fukushima Daiichi Nuclear Power Station
|
2011.10.10
|
1st floor of Reactor Building, Unit 1, Fukushima Daiichi Nuclear Power Station Cutoff operation for a spray system pipe of RPV
|
2011.10.10
|
1st floor of Reactor Building, Unit 1, Fukushima Daiichi Nuclear Power Station Cutoff operation for a spray system pipe of RPV
|
2011.10.8
|
Installation Work of Roof Panels for Reactor Building Covers at Unit 1 of Fukushima Daiichi Nuclear Power Plant
|
2011.10.8
|
Status of Fukushima Daiichi Nuclear Power Plants shown in photos
|
2011.10.7
|
View of spraying water after purification of accumulated water at Unit 5 and 6 of Fukushima Daiichi Nuclear Power Station on site
|
2011.10.1
|
Overview of Dust Collector System
|
2011.9.27
|
Picture of mock-up test for covering Spent Fuel Pool to remove debris on the roof of Reactor Building at Unit 4, Fukushima Daiichi Nuclear Power Station
|
2011.9.17
|
Fukushima Daiichi Nuclear Power Plant Photo Collection
|
2011.9.8
|
Enhancement of medical services at Fukushima Daiichi NPS
|
2011.8.17
|
Reporting from the grounds of Fukushima Daiichi Nuclear Power Station
|
2011.8.10
|
Status of iron frame construction for the reactor building cover of Unit 1 at Fukushima Daiichi Nuclear Power Station
|
2011.7.31
|
Air leakage at Main Exhaust Stack of Unit 4, Fukushima Daini Nuclear Power Station
|
2011.7.30
|
Completion of Installation of Supporting Structure under the Bottom of the Spent Fuel Pool in the Reactor Building at Fukushima Daiichi Nuclear Power Station Unit 4
|
2011.7.28
|
Video by Quince Robot within Fukushima Daiichi Nuclear Power Station Unit 3 reactor building
|
2011.7.27
|
Fukushima Daiichi Nuclear Power Station Reactor Building of Unit3 Site Investigation by Quince
|
2011.7.26
|
Installation of reactor building cover Unit 1, Fukushima Daiichi Nuclear Power Station
|
2011.7.26
|
The 2nd Cesium Adsorption Facility (SARRY)
|
2011.7.18
|
Fukushima Daiichi Nuclear Power Station Unit 3 Turbine Building Installation Work of Roof
|
2011.7.17
|
Appearance of the Roof for Countermeasure against Rainwater, Unit 3, Fukushima Daiichi
|
2011.7.12
|
The repaired part for chemical leakage of water treatment system(before/after repair)
|
2011.7.10
|
The repaired part for chemical leakage of water treatment system (coagulation settling facility)
|
2011.7.9
|
Fukushima Daiichi Unit3 - Investigation result of nitrogen injection point at R/B
|
2011.7.7
|
Trial fitting of the cover for Unit 1, Fukushima Daiichi Nuclear Power Station at Onahama port
|
2011.7.5
|
Construction Status of Mitigation of Contamination in the Ocean from Unit 1 to 4(Water intake sliding concrete plate in the screen)
|
2011.7.4
|
Fukushima Daiichi Nuclear Power Plant Setting steel sheet at the 1st floor of the unit 3 reactor building
|
2011.7.2
|
Cleanup work by using a robot in Unit 3 Reactor Building at Fukushima Daiichi Power Station
|
2011.6.30
|
Cleaning system for Unit 3, Fukushima Daiichi Nuclear Power Station
|
2011.6.30
|
Removal of Heavy Oil Tank No.1 at Fukushima Daiichi Nuclear Power Station
|
2011.6.23
|
Temporary Indicator Set-up at Unit 2
|
2011.6.20
|
Installation work of supporting structure at the bottom of Spent Fuel Pool
|
2011.6.10
|
Transportation of large tank to Fukushima Daiichi Nuclear Power Station
|
2011.6.8
|
Reactor Building, Unit 4, Fukushima Daiichi Nuclear Power Station Installation of support pillars at the bottom of the Spent Fuel Poo
|
2011.6.5
|
Spraying dust inhibitor over outside walls and roofs of Fukushima Daiichi Nuclear Power Station
|
2011.6.4
|
Fukushima Daiichi Nuclear Power Station Temporary reactor pressure indicators
|
2011.5.28
|
Spraying dust inhibitor at Fukushima Daiichi Nuclear Power Station
|
2011.5.17
|
Fukushima Daiichi Nuclear Power Station Current status of restoration work
|
2011.4.28
|
Fukushima Daiichi Nuclear Power Station
|
2011.4.11
|
Motion pictures of Fukushima Daiichi Nuclear Power Station
|
2011.4.11
|
Removal of Rubbles by Remotely Controlled Heavy Machinery (System 1)
|
2011.3.23
|
Grid line connection work to offsite power grid
|
2011.3.22
|
Water pumping using a concrete pumping car
|