Overview of the blocking operation of the units 1 - 4 openings
Upload dateNov 02,2011
![](/library/111102/111102_01.jpg)
Photo
![](/library/111102/111102_01t.jpg)
Stair at Unit 1 turbine building (1F) Before block
pictured on Jul 23,2011
pictured on Jul 23,2011
![](/library/111102/111102_02.jpg)
Stair at Unit 1 turbine building (1F) After Block
pictured on Oct 05,2011
pictured on Oct 05,2011
![](/library/111102/111102_03.jpg)
Stair at On-site Bunker Building (2F) Before block
pictured on Jul 29,2011
pictured on Jul 29,2011
![](/library/111102/111102_04.jpg)
Stair at On-site Bunker Building (2F) After Block (1)
pictured on Oct 09,2011
pictured on Oct 09,2011
![](/library/111102/111102_05.jpg)
Stair at On-site Bunker Building (2F) After Block (2)
pictured on Oct 09,2011
pictured on Oct 09,2011
![](/library/111102/111102_06.jpg)
Hatch at On-site Bunker Building (2F) Before block
pictured on Jul 29,2011
pictured on Jul 29,2011
![](/library/111102/111102_07.jpg)
Hatch at On-site Bunker Building (2F) After Block
pictured on Oct 09,2011
pictured on Oct 09,2011
![](/library/111102/111102_08.jpg)
Unit 1 turbine building : Entrance of heater room (1F) Before block
pictured on Jul 23,2011
pictured on Jul 23,2011
![](/library/111102/111102_09.jpg)
Unit 1 turbine building : Entrance of heater room (1F) After block
pictured on Oct 05,2011
pictured on Oct 05,2011
![](/library/111102/111102_10.jpg)
Process Main Building : Elevator room (1F) Before block
pictured on Jul 22,2011
pictured on Jul 22,2011
![](/library/111102/111102_11.jpg)
Process Main Building : Elevator room (1F) After Block
pictured on Oct 10,2011
pictured on Oct 10,2011
![](/library/111102/111102_12.jpg)
Unit 4 turbine building large machine hatch (photo from 2F) Before construction
pictured on Jul 15,2011
pictured on Jul 15,2011
![](/library/111102/111102_13.jpg)
Unit 4 turbine building large machine hatch (photo from 2F) After construction
pictured on Oct 12,2011
pictured on Oct 12,2011
![](/library/111102/111102_14.jpg)
Unit 2 turbine building (2F) : Turbine maintenance hatch Before block
pictured on Sep 06,2011
pictured on Sep 06,2011
![](/library/111102/111102_15.jpg)
Unit 2 turbine building (2F) : Turbine maintenance hatch After block
pictured on Oct 04,2011
pictured on Oct 04,2011
![](/library/111102/111102_16.jpg)
Opening near Unit 4 turbine building (2F) combination middle valve Before block
pictured on Jul 17,2011
pictured on Jul 17,2011
![](/library/111102/111102_17.jpg)
Opening near Unit 4 turbine building (2F) combination middle valve After block
pictured on Sep 30,2011
pictured on Sep 30,2011