Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: September 2012)
Upload dateOctober 2, 2012
![](/library/121002_01/121002_29.jpg)
Photo
![](/library/121002_01/121002_01t.jpg)
Functional check (Completed on September 27, 2012)
Photo taken on September 27, 2012
![](/library/121002_01/121002_02t.jpg)
Control board being lifted up by a crane truck
Photo taken on September 21, 2012
![](/library/121002_01/121002_03t.jpg)
High-voltage panel being lifted up by a crane truck
Photo taken on September 11, 2012
Photo taken on September 11, 2012
![](/library/121002_01/121002_04t.jpg)
Carry-in of the control board etc. into the building (Completed on September 21, 2012)
Photo taken on September 26, 2012
Photo taken on September 26, 2012
![](/library/121002_01/121002_05t.jpg)
1. Power panel being lifted up by a crane truck
Photo taken on September 3, 2012
Photo taken on September 3, 2012
![](/library/121002_01/121002_06t.jpg)
2. Carry-in of the power panel
Photo taken on September 3, 2012
Photo taken on September 3, 2012
![](/library/121002_01/121002_07t.jpg)
3. Power panel installation
Photo taken on September 3, 2012
Photo taken on September 3, 2012
![](/library/121002_01/121002_08t.jpg)
4. Power panel being fixed (Bolt installation)
Photo taken on September 3, 2012
Photo taken on September 3, 2012
![](/library/121002_01/121002_09t.jpg)
5. Power panel (P/C 2C-2) installation (Completed on September 11, 2012)
Photo taken on September 26, 2012
Photo taken on September 26, 2012
![](/library/121002_01/121002_10t.jpg)
Full view of the residual heat removal equipment cooling seawater system pump (B)
Photo taken on September 26, 2012
Photo taken on September 26, 2012
![](/library/121002_01/121002_12t.jpg)
Full view of the residual heat removal equipment cooling seawater system pump (C)
Photo taken on September 26, 2012
Photo taken on September 26, 2012
![](/library/121002_01/121002_14.jpg)
Functional check of power panel (P/C 3C-2) (Permanent installation completed on August 27, 2012)
Photo taken on August 27, 2012
Photo taken on August 27, 2012
![](/library/121002_01/121002_15t.jpg)
Switching to the permanent cable for the electric motor of the residual heat removal equipment cooling system pump (C)
Photo taken on September 13, 2012
Photo taken on September 13, 2012
![](/library/121002_01/121002_19t.jpg)
Full view of the residual heat removal equipment cooling seawater system pump (A)
Photo taken on September 13, 2012
Photo taken on September 13, 2012
![](/library/121002_01/121002_22t.jpg)
Carry-in of the control board
Photo taken on September 4, 2012
Photo taken on September 4, 2012
![](/library/121002_01/121002_23t.jpg)
Control board installation
Photo taken on September 4, 2012
Photo taken on September 4, 2012
![](/library/121002_01/121002_24t.jpg)
Discharge monitor (detector) installation
Photo taken on September 4, 2012
Photo taken on September 4, 2012
![](/library/121002_01/121002_25t.jpg)
Before opening the reactor
Photo taken on September 10, 2012
Photo taken on September 10, 2012
![](/library/121002_01/121002_26t.jpg)
Concrete hatch removal
Photo taken on September 10, 2012
Photo taken on September 10, 2012
![](/library/121002_01/121002_27t.jpg)
PCV lid removal
Photo taken on September 11, 2012
Photo taken on September 11, 2012
![](/library/121002_01/121002_28t.jpg)
Loosening the RPV stud bolts
Photo taken on September 13, 2012
Photo taken on September 13, 2012
![](/library/121002_01/121002_29t.jpg)
RPV lid removal
Photo taken on September 14, 2012
Photo taken on September 14, 2012
![](/library/121002_01/121002_30t.jpg)
Steam dryer removal
Photo taken on September 19, 2012
Photo taken on September 19, 2012
![](/library/121002_01/121002_31t.jpg)
Steam-water separator removal
Photo taken on September 21, 2012
Photo taken on September 21, 2012
![](/library/121002_01/121002_32t.jpg)
After the reactor was opened
Photo taken on September 22, 2012
Photo taken on September 22, 2012
![](/library/121002_01/121002_33t.jpg)
Trace of contact (1)
Photo taken on September 11, 2012
Photo taken on September 11, 2012
![](/library/121002_01/121002_34t.jpg)
Trace of contact (2)
Photo taken on September 11, 2012
Photo taken on September 11, 2012
![](/library/121002_01/121002_36t.jpg)
Seismic control oil damper placed on the ground (before being lifted up)
Photo taken on April 20, 2012
Photo taken on April 20, 2012
![](/library/121002_01/121002_37t.jpg)
Before the support point was detached
Photo taken on September 5, 2012
Photo taken on September 5, 2012
![](/library/121002_01/121002_38t.jpg)
After the support point was detached
Photo taken on September 7, 2012
Photo taken on September 7, 2012
![](/library/121002_01/121002_39t.jpg)
Seismic control oil damper being lifted up
Photo taken on April 20, 2012
Photo taken on April 20, 2012
![](/library/121002_01/121002_40t.jpg)
Seismic control oil damper installation
Photo taken on April 20, 2012
Photo taken on April 20, 2012
![](/library/121002_01/121002_41t.jpg)
Seismic control oil damper installation completed
Photo taken on April 20, 2012
Photo taken on April 20, 2012
Video
Opening Unit 4 Reactor at Fukushima Daini Nuclear Power Station(17:44)
Play Video / Download(126MB)