Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: August 2012)
Upload dateSeptember 3, 2012

Photo

Generator stator being lifted up by a crane car
Photo taken on August 7, 2012
Photo taken on August 7, 2012

Generator stator being lifted down into the building
Photo taken on August 7, 2012
Photo taken on August 7, 2012

Generator stator being moved
Photo taken on August 8, 2012
Photo taken on August 8, 2012

Generator stator being installed
Photo taken on August 8, 2012
Photo taken on August 8, 2012

Generator rotor being lifted up
Photo taken on August 20, 2012
Photo taken on August 20, 2012

Generator rotor being lifted down into the building
Photo taken on August 20, 2012
Photo taken on August 20, 2012

Generator rotor being moved
Photo taken on August 21, 2012
Photo taken on August 21, 2012

Generator rotor being inserted into the generator stator (1)
Photo taken on August 22, 2012
Photo taken on August 22, 2012

Generator rotor being inserted into the generator stator (2)
Photo taken on August 22, 2012
Photo taken on August 22, 2012

Generator rotor being inserted into the generator stator (3)
Photo taken on August 22, 2012
Photo taken on August 22, 2012

Generator rotor being inserted into the generator stator (4) (From above)
Photo taken on August 22, 2012
Photo taken on August 22, 2012

Generator rotor being inserted into the generator stator (5)
Photo taken on August 22, 2012
Photo taken on August 22, 2012

Generator installation completed
Photo taken on August 31, 2012
Photo taken on August 31, 2012

Seismometer function check (Second basement of Unit 1 Reactor Building)
Photo taken on July 25, 2012
Photo taken on July 25, 2012

Function check
Photo taken on August 27, 2012
Photo taken on August 27, 2012
Video
Fukushima Daini Nuclear Power Station Unit 1 Emergency Diesel Generator (A) Carry-in and Installation(6:12)