Progress Status of Fukushima Daini Nuclear Power Station Restoration Plan (Monthly Report: March 2013)


●Permanent installation of the power panel (M/C 1HPCS) in Unit 1 Reactor Building Annex (March 1)
・After function check
[Permanent installation completed on March 1, 2013]
(Photo taken on March 12, 2013)

●Permanent installation of the emergency diesel generator (H) facilities in Unit 1 Reactor Building Annex (March 21)
・Trial operation (control panel)
[Permanent installation completed on March 21, 2013]
(Photo taken on March 19, 2013)

[Permanent installation completed on March 21, 2013]
(Photo taken on March 21, 2013)

[Permanent installation completed on March 21, 2013]
(Photo taken on March 21, 2013)

●Permanent installation of the charger and battery of the DC power supply (H) in Unit 1 Reactor Building Annex (March 14)
・After function check (charger panel)
[Permanent installation completed on March 12, 2013]
(Photo taken on April 1, 2013)

[Permanent installation completed on March 14, 2013]
(Photo taken on March 14, 2013)

●Permanent installation of the electric motor of the residual heat removal system (A) in Unit 1 Reactor Building (March 15)
・Trial operation
[Permanent installation completed on March 15, 2013]
(Photo taken on March 15, 2013)

●Permanent installation of the electric motors of the residual heat removal system cooling systems (B and D) in Unit 1 Seawater Heat Exchanger Building (March 1)
・Removal of temporary cable
(Photo taken on February 26, 2013)

[Permanent installation completed on March 1, 2013]
(Photo taken on March 14, 2013)

●Permanent installation of the electric motors of the residual heat removal system cooling seawater systems (B and D) in Unit 1 Seawater Heat Exchanger Building (March 4)
・Before switching to the permanent cable
(Photo taken on February 25, 2013)

[Permanent installation completed on March 4, 2013]
(Photo taken on March 14, 2013)

●Permanent installation of the electric motor of the emergency diesel generator cooling system (B) in Unit 1 Seawater Heat Exchanger Building (March 1)
・Before switching to the permanent cable
(Photo taken on February 25, 2013)

[Permanent installation completed on March 1, 2013]
(Photo taken on April 1, 2013)

●Permanent installation of the electric motor of the high pressure reactor core spray system in Unit 1 Reactor Building (March 25)
[Permanent installation completed on March 25, 2013]
(Photo taken on March 25, 2013)

●Permanent installation of the electric motor of the high pressure reactor core spray system component cooling system in Unit 1 Seawater Heat Exchanger Building (March 14)
[Permanent installation completed on March 14, 2013]
(Photo taken on March 14, 2013)

●Permanent installation of the electric motor of the high pressure reactor core spray system component cooling seawater system in Unit 1 Seawater Heat Exchanger Building (March 18)
・Trial operation
[Permanent installation completed on March 18, 2013]
(Photo taken on March 18, 2013)

●Permanent installation of the electric motors of the reactor component cooling systems (A and B) in Unit 1 Seawater Heat Exchanger Building (March 8)
・Switching to the permanent cable completed for the electric motor of the reactor component cooling system (A)
[Permanent installation completed on March 8, 2013]
(Photo taken on March 14, 2013)

●Earthquake Training and Comprehensive Fire Fighting Training at Fukushima Daini Nuclear Power Station
・Evacuation guidance training
(Photo taken on March 21, 2013)

(Photo taken on March 21, 2013)

(Front: self defense fire-fighting team member, back: public fire-fighting team member)
(Photo taken on March 21, 2013)

●Installation of the Emergency Power Supply on the Hill (Gas Oil Tank on the Hill) and the Permanent Cable
◎Deployment of a gas oil tank on the hill and air-cooled gas turbine generator cars
・Feeding oil to the gas oil tank on the hill (underground)
[Photo taken on March 27, 2013]

・Air-cooled gas turbine generator car
[Photo taken on April 1, 2013]
Photo taken by Tokyo Electric Power Company
Category
■Search by status/measures
Others